Singapore Pilot MBT Plant is located in Tuas Industrial Zone, covering an area of 10,324 square meters. Led by the Singapore National Environment Agency (NEA), the project aims to enhance resource recovery and Municipal Solid Waste (MSW) utilization, utilize land resources and extend the service life of Singapore's only landfill site. When completed, the project will be one of only five MBT projects in Asia.

We are the EPC contractor of the pre-processing system in this project. The MBT plant can handle MSW 500 tons/day, the expected working hours are 16 per day with two shifts.

The processing phase can be divided into pre-sorting phase, biodrying phase and post-sorting phase. Furthermore, the plant is equipped with deodorization system, dust suppression system, sewage treatment system. 

ARTWORK OF TECHNOLOGY

The project integrates the world's advanced MBT technology. The project also has automated sorting system, and automated overhead crane in the biological drying zone. Despite the small covering area of the project, the combination of advanced technology and multi-storey design makes it possible to achieve multifunctional, large-scale MSW treatment in a small space. The whole project is like a piece of artwork with technology.

Biodrying process is the core technology of the plant, due to the high moisture content of MSW in Singapore, biodrying process can reduce the moisture content to the low level within 8-9 days by automatic controlling system. 

The main output materials are recovered plastics, recovered metals, Solid Recovered Fuel (SRF), inert materials.

THE HIGHEST STANDARDS

In this project, the customer selected the most stringent European standards and American standards as the reference. Luca Zhou, technical engineer of the project, said: "The customer's high requirements were reflected in all aspects of equipment manufacturing, project construction and production capacity. But we did not see these requirements as challenges, on the contrary, we see them as motivations."

"Through reasonable collocation of ballistic screen, optical separator, air sifter and other equipment, we met the customer's requirements for recovery rate." He mentioned.

This project was a radiative and exemplary project for other projects of JONO Enviro in Southeast Asia. It verified the ability of JONO Enviro to implement MSW treatment project with the highest standards.

新加坡MBT.jpg